Columbia Basin Fish and Wildlife Program Columbia Basin Fish and Wildlife Program
SOW Report
Contract 14880 REL 4: 2003-017-00 EXP INTEGRATED STATUS & EFFECTIVENESS MONITORING
Project Number:
Title:
Integrated Status and Effectiveness Monitoring Program (ISEMP)
BPA PM:
Stage:
Complete
Area:
Province Subbasin %
Basinwide - 100.00%
Contract Number:
14880 REL 4
Contract Title:
2003-017-00 EXP INTEGRATED STATUS & EFFECTIVENESS MONITORING
Contract Continuation:
Previous: Next:
14880 REL 2: 2003-017-00, INTEGRATED STATUS & EFFECTIVENESS MONITORING
  • 27480 REL 1: 200301700 EXP ISEMP COORDINATION FOR WENATCHEE/ENTIAT - TERRAQUA
Contract Status:
Closed
Contract Description:
Project #2003-017-00 seeks to develop two novel monitoring and evaluation programs: (i) subbasin-scale pilot status and trend monitoring efforts for anadromous salmonids and their habitat in the Wenatchee/Entiat, John Day and South Fork Salmon River basins, and (ii) effectiveness monitoring for suites of habitat restoration projects in selected watersheds within the three target subbasins.  This work  critical for implementing the 2000 NMFS FCRPS Biological Opinion (RPA Actions 180, 181, and 183) (BiOp)  builds on current status and trend monitoring programs within each of these basins.  Several regional and local organizations are funding and implementing these programs.  In short, this project will integrate existing and new monitoring and evaluation activities in three pilot subbasins to help ensure that provisions of the BiOp are satisfied.

This contract will enable the Bonneville Power Administration (Bonneville) to implement Project #2003-017-00 in the Wenatchee subbasin.  Specifically, this work will: coordinate cooperative agreements under which the salmonid and habitat status, trend and effectiveness monitoring program design, development and implementation will occur; document the implementation of several scientific studies conducted under Project #2003-017-00; coordinate work being conducted in the Wenatchee/Entiat with the other Pilot subbasins; develop a field manual to support continued work under this Project; analyze macroinvertebrate samples collected in the Wenatchee/Entiat; perform effectiveness monitoring in the Entiat subbasin; develop a protocol for sampling depth-fines; conduct selected repeat habitat sampling in the Wenatchee to generate variability estimates; and project management.
Account Type(s):
Expense
Contract Start Date:
07/01/2005
Contract End Date:
06/30/2006
Current Contract Value:
$187,396
Expenditures:
$187,396

* Expenditures data includes accruals and are based on data through 31-Oct-2024.

Env. Compliance Lead:
Contract Contractor:
Work Order Task(s):
Contract Type:
Release
Pricing Method:
Time and Materials
Click the map to see this Contract's location details.

No photos have been uploaded yet for this Contract.

Full Name Organization Write Permission Contact Role Email Work Phone
Paul Krueger Bonneville Power Administration Yes F&W Approver pqkrueger@bpa.gov (503) 230-5723
Gerald McClintock Bonneville Power Administration Yes COR gmcclintock@bpa.gov (503) 230-5375
Mark Nadeau Bonneville Power Administration Yes Contracting Officer mhnadeau@bpa.gov (503) 230-5889
Pamela Nelle Terraqua, Inc. No Administrative Contact pamela@terraqua.biz (509) 885-8143
Michael Ward Terraqua, Inc. Yes Contract Manager mike@terraqua.biz (509) 486-2426
Nancy Weintraub Bonneville Power Administration No Env. Compliance Lead nhweintraub@bpa.gov (503) 230-5373


Viewing of Work Statement Elements

Deliverable Title WSE Sort Letter, Number, Title Start End Concluded
Meeting minutes / Coordination reports A: 118. 4.1 ISEMP Coordination 06/30/2006 08/16/2006
Implementation Strategy for the Wenatchee Integrated Monitoring Program Addendum B: 174. 4.2 Project Tracking Document 06/30/2006 08/16/2006
Data dictionary or model C: 160. 4.3 Data Management System Development 06/30/2006 08/16/2006
Meeting Minutes D: 118. 4.4 Pilot Subbasin Coordination 06/30/2006 08/16/2006
Final Field Manual E: 174. 4.5 Field Manual Development 06/23/2006 08/16/2006
Macroinvertebrate Analysis F: 157. 4.6 Macroinvertebrate Analysis 04/30/2006 06/08/2006
Field Data Validation Report G: 157. 4.7 Entiat Effectiveness Monitoring 06/30/2006 08/16/2006
Depth-fines Protocol H: 157. 4.8 Develop Depth-Fines Protocol 06/30/2006 08/16/2006
Final Channel Characterization Data I: 157. 4.9 Repeat Sampling in Wenatchee 06/30/2006 07/17/2006
BPA Project Administration Requirements J: 119. 4.10a Project Management 06/30/2006 08/16/2006
Environmental Compliance supporting documentation K: 165. 4.10d Environmental compliance 08/01/2006 06/27/2006

Viewing of Implementation Metrics
Viewing of Environmental Metrics Customize

Primary Focal Species Work Statement Elements
All Anadromous Salmonids
  • 1 instance of WE 157 Collect/Generate/Validate Field and Lab Data
Chinook (O. tshawytscha) - Upper Columbia River Spring ESU (Endangered)
  • 2 instances of WE 174 Produce Plan
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data
Steelhead (O. mykiss) - Upper Columbia River DPS (Threatened)
  • 2 instances of WE 174 Produce Plan
  • 3 instances of WE 157 Collect/Generate/Validate Field and Lab Data

Sort WE ID WE Title NEPA NOAA USFWS NHPA Has Provisions Inadvertent Discovery Completed
A 118 4.1 ISEMP Coordination
B 174 4.2 Project Tracking Document
C 160 4.3 Data Management System Development
D 118 4.4 Pilot Subbasin Coordination
E 174 4.5 Field Manual Development
F 157 4.6 Macroinvertebrate Analysis
G 157 4.7 Entiat Effectiveness Monitoring
H 157 4.8 Develop Depth-Fines Protocol
I 157 4.9 Repeat Sampling in Wenatchee
J 119 4.10a Project Management
K 165 4.10d Environmental compliance
L 185 4.10b Monthly online milestone status report via Pisces